55 Cutters Way - Index of Working Drawings

NOTE: Page will automatically refresh every 2 minutes.

Drawing 1

Upper Level Floor Plan
Updated drawing 1E. Published 18/5/16

Drawing 2

Lower Level Floor Plan
Updated drawing 2D. Published 18/5/16

Drawing 3

North and South Elevations
Updated drawing 3B. Published 18/5/16

Drawing 4

East and West Elevations
Updated drawing 4B. Published 13/5/16

Drawing 5

Section A-A
Updated drawing 5A. Published 9/5/16

Drawing 6

Section B-B
Updated drawing 6B. Published 18/5/16

Drawing 7

Section C-C
Updated drawing 7A. Published 9/5/16

Drawing 8

Section D-D
Updated drawing 8B. Published 18/5/16

Drawing 9

Floor Framing plan

Drawing 10

Floor Framing sections 1, 2 & 3
Updated drawing 10A. Published 9/5/16

Drawing 11

Floor Framing detail Sections 1 & 2
Updated drawing 11B. Published 10/5/16

Drawing 12

Floor Framing detail Sections 3 & 4
Updated drawing 12A. Published 18/5/16

Drawing 13

Roof plan
Updated drawing 13A. Published 9/5/16

Drawing 14

Roof Framing plan

Drawing 15

Front Barge detail
Updated drawing 15A. Published 9/5/16

Drawing 16

Eaves detail
Updated drawing 16B. Published 13/5/16

Drawing 17

West Verandah Eaves detail
Updated drawing 17B. Published 18/5/16

Drawing 18

Window schedule
Updated drawing 18C. Published 18/5/16

Drawing 19

Bifold Door Schedule
Updated drawing 19B. Published 10/5/16

Drawing 20

Site Plan
Updated drawing 20C. Published 18/5/16

Drawing 21

Driveway cross section

Drawing 22

Entrance verandah eaves detail
First published 18/5/16

Drawing 23

Electrical layout - Upper level See also Drawing 25 Electrical Legend
Published 18/5/16

Drawing 24

Electrical layout - Lower level See also Drawing 25 Electrical Legend Published 18/5/16

Drawing 25

Electrical Drawings Legend
Published 18/5/16

Drawing 26

Master Bedroom Deck detail
First published 18/5/16

 

Additional Supporting Documents

Engineering

The engineering requirements are being overseen by Geo Consulting (Scott Brimelow). When completed their reports and requirements will be published in this space.

 

Building Approval

Suncoast Building Approvals have been appointed (Michael Grummett). When completed their reports will be published in this space.

Proprietors Specifications

ITEM

LINKS

ALLOWANCE

Timber Flooring

Carpet

Tiles

Air Conditioning

Stairs

Balustrade (ex stairs)

Solar Hot Water

Solar Power

Doors

Windows

Kitchen (Cabinet)

Kitchen (Appliances)

Light Fittings

Ceiling Fans

Exhaust Fans

Batroom Fittings

Garage Door

Stone Masonry

Fencing

x

x

x

x

x

x

Additional Reference Material

ITEM

LINKS

ALLOWANCE

x

x

x

x

x

x

x

x

x

x

x

x

x